Water Transmission Line

  • Project : Water Transmission Line
  • Contractor : Al Nasr Contracting Company
  • Consultant : Tebodin Middle East Ltd.
  • Location : Sowwah Island, Abu Dhabi
  • Duration of Work : 13/10/12 - 19/01/13
 

Water Tank and Pump Room

  • Project : Water Tank and Pump Room
  • Contractor : National Development Foundation
  • Consultant :AECOM
  • Location : Yas Island, Abu Dhabi
  • Duration of Work : 11/04/13 - 18/04/13
 

Irrigation Tank Construction

  • Project : Irrigation Tank Construction
  • Contractor :Al Futtaim Carrilion
  • Consultant :Khatib & Alami
  • Location : Downtown Dubai
  • Duration of Work : 08/06/13 - 15/06/13



Click on image to Enlarge
Click on image to Enlarge
Click on image to Enlarge
Click on image to Enlarge
 

Dubai Mall Storm Water Drainage Discharge

  • Project : Dubai Mall Storm Water Drainage Discharge
  • Contractor :Al Futtaim Carrilion
  • Consultant :Khatib & Alami
  • Location : Downtown Dubai
  • Duration of Work : 23/04/13 - 04/04/13